1.The project manager has created the WBS and the management plan. What is the next process to be used in order to achieve the project?
A. Gain approval for project charter.
B. Implement change control.
C. Direct and manage project execution.
D. Perform quality control plan.
项目经理己经创建了WBS和项目管理计划。若要达到项目目标,需要使用的下一个过程是什么?
A. 让项目章程获得批准
B. 实施变更控制
C. 指导与管理项目工作
D. 实施质量控制
2.The method of calculating the EAC by adding the remaining project budget (modified by a performance factor) to the actual to date is used most often when the
A. Current variances are viewed as atypical ones
B. Original estimating assumptions are no longer reliable because conditions have changed
C. Current variances are viewed as typical of future variances
D. Original estimating assumptions are considered to be fundamentally flawed
在什么时候通过增加剩余项目的预算(利用业绩表现修正的)达到当前实际的计算 EAC的方法最经常使用?
A.在偏离被视为非典型的偏离的时候
B.由于条件发生变化,初始的估计假定不再可信的时候
C.当前的偏离被视为未来偏离的代表的时候
D.初始的估计假定被认为存在根本性缺陷的时候