1. Which of the following indicates the required cost performance in order to complete the project on budget?
A. TCPI
B. CPI
C. EAC
D. SPI
1. 下列哪项表示用来完成预算项目需要的成本绩效?
A. TCPI
B. CPI
C. EAC
D. SPI
2. While reviewing project procurement and accounting records for your project, you discover there is a pattern of unauthorized expenses by a specific resource. These expenses are not within the scope of the project and were somewhat camouflaged within a number of large and complicated expense reports. What do you do?
A. If the total expenses are less than percent of the project budget, do nothing
B. Fire the resource
C. Notify the appropriate management immediately
D. Confront the resource
2. 在审核项目的项目采购和会计记录时,你发现有一个未经授权的特定资源。这些费用不在项目的范围内,并且在一些庞大而复杂的费用报告中被隐瞒了。你需要做什么工作?
A. 如果总费用少于项目预算的百分之一,什么都不做
B. 开除资源
C. 立即通知相关的管理层
D. 面对资源
3. Visiting a construction site to ensure the completed work is the same work specified in the requirements is:
A. Milestone
B. Scope validation
C. Variance Analysis
D. Requirements traceability
3. 参观建筑工地以确保完成的工作与需求中规工作是否相同,这属于( ):
A. 里程碑
B. 确认范围
C. 偏差分析
D. 需求追踪