1、During a project status meeting, two managers discuss the features of the deliverables for the next milestone. If the team members deliver what they planned, the deliverables will not meet expectations.To ensure the project delivers all the business critical features, what should the project manager do next?
A.Conduct a review of the requirements traceability matrix
B.Analyze the compliance matrix to resolve the difference
C.Recognize it as a risk and add it to the risk log
D.Perform a variance analysis
在项目状态会议期间,两名经理讨论下一个里程碑的可交付成果功能。如果团队成员按计划交付,可交付成果将不符合期望。若要确保项目交付所有业务关键功能,项目经理下一步应该怎么做?
A.开展需求跟踪矩阵的审查
B.分析合规性矩阵,解决差异
C.将其识别为一个风险,并将其添加到风险日志
D.执行偏差分析
2、Early in a project's life cycle, a project manager plans to enhance the project's chance of success by building partnerships and coalitions with project stakeholders. What should the project ragger do to achieve this?
A.Create a stakeholders engagement assessments matrix to identify gaps between current and desired engagement levels.
B.Map the interest levels of each stakeholder to the project's objectives.
C.Document and clarify stakeholder roles by developing a responsible, accountable, consult, and inform (RACI) matrix
D.Gather and analyze information on potential stakeholders to determine whose interests should be considered.
在项目生命周期早期,项目经理打算通过与项目相关方建立合作伙伴关系和联合体,提高项目的成功概率。若要实现这一点,项目经理应该怎么做?
A.创建项目相关方参与评估矩阵,识别当前参与程度与所需参与程度之间的差距。
B.将每位项目相关方的利益层级与项目目标映射。
C.通过制定一份执行、负责、咨询和知情(RACI)矩阵记录并澄清相关方的角色。
D.收集并分析潜在相关方的相关信息,确定应考虑谁的利益。
3、Company a awards a fixed price with economic price adjustment contract(FP-EPA) to company B. after two months, company B informs company A that the cost of some of the products has risen markedly. These products are covered under the EPA clause.What is the impact to the project?
A.Company B mustmeet its obligations and cover all costs
B.Company A mustmeet its obligations and cover all costs
C.Contract must be renegotiated, because the products relate to the EPA clause
D.Contract must be terminated, because the products relate to the EPA clause
公司A向公司B授予一份总价加经济价格调整合同(FP-EPA)。两个月后,公司B通知公司A某些产品的成本大幅度上涨。这些产品包含在EPA条款中。这对项目会产生什么影响?
A.公司B必须履行其义务并承担所有成本
B.公司A必须履行其义务并承担所有成本
C.公司必须重新谈判,因为产品与EPA条款有关
D.合同必须终止,因为产品与EPA条款有关