欢迎来到思摩特项目管理官方网站! 南京 | 镇江 | 扬州 | 常州 | 芜湖 | 马鞍山 | 滁州 等地区指定项目管理培训中心

加入收藏

    联系我们
  • 全国24小时免费咨询电话:
    400-805-8908

    welcome@smartpm.com.cn

    • 长春PMP培训机构推荐|模拟题

  • 发布时间:2019-12-03 09:07:36  来源:思摩特 www.smartpm.com.cn  浏览量:0
  • 编辑导读:本文为大家介绍的是长春PMP培训机构推荐|模拟题,下面是长春PMP推荐机构密训题的具体内容,供大家参考,更多PMP考试相关资讯可关注思摩特项目管理

    本文为大家介绍的是长春PMP培训机构推荐|模拟题,下面是长春PMP推荐机构密训题的具体内容,供大家参考,更多PMP考试相关资讯可关注思摩特项目管理

    思摩特PMP办学资质

    ↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证

     

    1、During a project status meeting, two managers discuss the features of the deliverables for the next milestone. If the team members deliver what they planned, the deliverables will not meet expectations.To ensure the project delivers all the business critical features, what should the project manager do next?

     

    A.Conduct a review of the requirements traceability matrix

     

    B.Analyze the compliance matrix to resolve the difference

     

    C.Recognize it as a risk and add it to the risk log

     

    D.Perform a variance analysis

     

    在项目状态会议期间,两名经理讨论下一个里程碑的可交付成果功能。如果团队成员按计划交付,可交付成果将不符合期望。若要确保项目交付所有业务关键功能,项目经理下一步应该怎么做?

     

    A.开展需求跟踪矩阵的审查

     

    B.分析合规性矩阵,解决差异

     

    C.将其识别为一个风险,并将其添加到风险日志

     

    D.执行偏差分析

    长春PMP推荐PMP机构精选题

    2、Early in a project's life cycle, a project manager plans to enhance the project's chance of success by building partnerships and coalitions with project stakeholders. What should the project ragger do to achieve this?

     

    A.Create a stakeholders engagement assessments matrix to identify gaps between current and desired engagement levels.

     

    B.Map the interest levels of each stakeholder to the project's objectives.

     

    C.Document and clarify stakeholder roles by developing a responsible, accountable, consult, and inform (RACI) matrix

     

    D.Gather and analyze information on potential stakeholders to determine whose interests should be considered.

     

    在项目生命周期早期,项目经理打算通过与项目相关方建立合作伙伴关系和联合体,提高项目的成功概率。若要实现这一点,项目经理应该怎么做?

     

    A.创建项目相关方参与评估矩阵,识别当前参与程度与所需参与程度之间的差距。

     

    B.将每位项目相关方的利益层级与项目目标映射。

     

    C.通过制定一份执行、负责、咨询和知情(RACI)矩阵记录并澄清相关方的角色。

     

    D.收集并分析潜在相关方的相关信息,确定应考虑谁的利益。

    长春PMP培训机构练习题

    3、Company a awards a fixed price with economic price adjustment contract(FP-EPA) to company B. after two months, company B informs company A that the cost of some of the products has risen markedly. These products are covered under the EPA clause.What is the impact to the project?

     

    A.Company B mustmeet its obligations and cover all costs

     

    B.Company A mustmeet its obligations and cover all costs

     

    C.Contract must be renegotiated, because the products relate to the EPA clause

     

    D.Contract must be terminated, because the products relate to the EPA clause

     

    公司A向公司B授予一份总价加经济价格调整合同(FP-EPA)。两个月后,公司B通知公司A某些产品的成本大幅度上涨。这些产品包含在EPA条款中。这对项目会产生什么影响?

     

    A.公司B必须履行其义务并承担所有成本

     

    B.公司A必须履行其义务并承担所有成本

     

    C.公司必须重新谈判,因为产品与EPA条款有关

     

    D.合同必须终止,因为产品与EPA条款有关

    长春PMP培训机构精选预测题

     

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部