欢迎大家来到思摩特长春PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. During the development of the project stakeholder engagement plan, a project manager is usually dependent on the voice of the project stakeholders to obtain expert opinion. Which of the following is an important tool available to the project manager for gathering and organizing stakeholders’ information?
A. Fishbone diagrams
B. Control charts
C. Histograms
D. Focus groups
1.在制定相关方参与计划期间,项目经理经常需要听取项目相关方的声音,以获取专家意见。以下哪一项是对项目经理收集和组织相关方信息来说重要的工具?
A. 鱼骨图
B. 控制图
C. 直方图
D. 焦点小组
2.During which of the following project processes do key stakeholders engage with the project for the first time?
A. Develop Project Charter
B. Identify Stakeholders
C. Collect Requirements
D. Plan Stakeholder Engagement
2. 在哪个相关过程期间,关键相关方首次参与项目?
A. 制定项目章程
B. 识别相关方
C. 收集需求
D. 规划相关方参与
3. Which of the following components of a project scope statement is useful in reducing scope creep?
A. Acceptance criteria
B. Deliverables
C. Scope description
D. Exclusions
3. 以下哪一个项目范围说明书的组件有利于减少范围蔓延?
A. 验收标准
B. 可交付成果
C. 范围描述
D. 除外责任