1.Who is responsible for defining "finish"?
- A. Team
- B、PO
- C. Manager
- D. Project Manager
谁负责定义“完成”?
- A、团队
- B、PO
- C、管理者
- D、项目经理
2.Which of the following is an example of visualization in lean?
- A. Business value delivery chart
- B. Product specification
- C. Automatic code coverage report
- D. Scrum of Scrum Report
以下哪个是精益中可视化的例子?
- A、商业价值交付图表
- B、产品技术规范
- C、自动代码覆盖报告
- D、scrum of scrum 报告
3.When setting the iteration length, which three criteria should we pay attention to?
- A. The completion time of user stories, the construction and testing time of user stories, and the acceptability of stories by product teams
- B. Time frame of release plan, cost of function delivery to market, acceptability of story by product team
- C. Modules for delivering user value, time for building and testing user stories, and acceptability of stories by product teams
- D. Classified product requirements, time to complete the requirements, cost of function delivery to the market
在设置迭代长度的时候,以下哪 3 个标准需要关注?
- A、用户故事的完成时间、用户故事的构建和测试时间、产品团队对故事的可接受性
- B、版本发布计划的时间框、功能交付市场的成本、产品团队对故事的可接受性
- C、交付用户价值的模块、用户故事的构建和测试时间、产品团队对故事可接受性
- D、分类的产品需求、完成需求的时间、功能交付市场的成本