1. Which process group corresponds to the “do” part of the plan-do-check-act cycle?
A. Closing
B. Monitoring and Controlling
C. Planning
D. Executing
1. 哪个过程组对应于“计划-实施-检查-处理”周期的“实施”部分?
A. 收尾
B. 监控
C. 规划
D. 执行
2. Chris is managing a construction project. The project team is currently developing the “as built” construction drawings to be supplied to the client as required by the contract. Which of the following phases is Chris’ project most likely in?
A. Initiating
B. Planning
C. Closing
D. Executing
2. 克里斯正在管理一个建筑项目,项目团队目前正在制定已竣工的施工图,并按照合同的要求提供给客户。以下哪个阶段是克里斯最可能参与的项目?
A. 启动
B. 计划
C. 收尾
D. 执行
3. You have recently become the project manager for a construction project. You are a new hire in your company and are unaware of the organizational project management standards. Which of the following can help you get a head start on your project?
A. Communicate with other project managers in your organization
B. Review the PMBOK guide thoroughly
C. Develop the project charter and get it approved
D. Consult the lessons learned from our previous similar projects
3. 你最近成为了一个建设项目的项目经理。你新来到这家公司,不知道组织的项目管理标准。以下哪项可以帮助你在项目中取得领先?
A. 与组织内的其他项目经理沟通
B. 彻底检查PMBOK指南
C. 制定项目章程并获得批准
D. 参考以前类似项目的经验教训