欢迎大家来到思摩特芜湖PMP培训机构,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. If an investment in a project returns 15 percent annually, how much should you invest to get $5 million by the end of the fifth year?
A. 2485884
B. 2857143
C. 2501376
D. 2685292
1. 如果投资一个项目,年回报是15%,要在第5年末获得5百万的收入,那么你应该投资多少钱?
A. 2485884
B. 2857143
C. 2501376
D. 2685292
2. A business is considering more than a dozen infrastructure upgrade projects. These projects, once delivered, will add to the organization’s overall performance but will not contribute to any of the revenue streams. Prior to initiating any such project, the value of the project to the organization must be determined. Which of the following is the most important factor to consider in such a scenario?
A. Net Present Value (NPV) of the projects
B. Internal Rate of Return (IRR) of the projects
C. Alignment with the strategic goals
D. Investment requirement
2. 一家企业正在考虑十几个基础设施升级项目。这些项目,一旦交付,将增加组织的整体业绩,但不会有助于任何收入流。在启动任何此类项目之前,必须确定项目对组织的价值。在这种情况下,下列哪一个因素是最重要的考虑因素?
A. 项目的NPV
B. 项目的IRR
C. 与组织战略目标的匹配
D. 投资需求
3. If a project manager believes that a particular subcontract needs to be terminated, which of the following can provide guidance on the contract termination procedure?
A. The contract termination procedures in the organizational process assets
B. The termination clause of the specific subcontract
C. The change control procedures in the project management plan
D. The contract termination procedures in the project procurements management plan
3. 如果一个项目经理认为一个特定的分包合同需要终止,下列哪一个可以为合同终止程序提供指导?
A. 组织过程资产中合同终止程序
B. 具体分包合同的终止条款
C. 项目管理计划中的变更控制程序
D. 项目采购管理计划中的合同终止程序