欢迎大家来到思摩特天津PMP考试认证培训,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. You are working with your team and are looking at the cost risks in the project. You and your team are currently creating a tornado diagram for the project risks. You do this as a part of which of the following processes?
A. Qualitative Risk Analysis
B. Risk Response Planning
C. Quantitative Risk Analysis
D. Monitor Risks
1. 你正在与你的团队合作,并且正在研究项目中的成本风险。你和你的团队目前正在为项目风险创建一个龙卷风图。你将此作为以下哪个过程中的一部分?
A. 定性风险分析
B. 风险应对计划
C. 定量风险分析
D. 监督风险
2. In your weekly status reports, you report the earned value for the project. This information is essential for you and the stakeholders to gauge the progress of the project. What process group is the cost and schedule control part of?
A. Closing
B. Planning
C. Executing
D. Monitoring and Controlling
2. 在你的每周状态报告中,你报告了项目的挣值。这些信息对于你和相关方测量项目的进展来说是非常重要的。控制成本和控制进度过程属于哪一个过程组?
A.收尾
B.规划
C.执行
D.监控
3. Your construction project is in execution, and you require a major change to one of your supplier agreements. Can you directly make this change with mutual consent of the supplier during the Control Procurements process, or do you have to visit the Perform Integrated Change Control process, as well?
A. The change request needs to be approved through the Control Procurements process prior to making the change through the Integrated Change Control process.
B. The change request can be directly processed through the Control Procurements process since the change requests only affects a particular supplier agreement.
C. The Control Procurements process is about identifying variances. The supplier contract can directly be altered through the Perform integrated Change Control process.
D. The change request needs to be approved through the Perform Integrated Change Control process prior to making the change through the Control Procurements process.
3. 你的建筑项目正在执行中,你需要对一个供应商的协议进行重大变更。在控制采购过程中,你是否可以在供应商的双方同意下的情况下直接做出更改,或者你同样也需要通过实施整体变更控制来变更?
A. 变更请求需要通过控制采购流程批准,然后通过实施整体变更控制过程进行变更
B. 变更请求可以通过控制采购流程直接处理,因为变更请求只影响特定的供应商协议
C. 控制采购过程是关于识别偏差的,供应商合同可以直接通过实施整体变更控制改变
D. 在通过控制采购过程进行变更之前,需要通过实施整体变更控制过程来批准变更请求