欢迎大家来到思摩特苏州PMP远程培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1. During the Control Procurements process, a number of documents might get updated due to various reasons. Which of the following components of the project management plan is least likely to get updated during this process?
A. Quality management plan
B. Procurement management plan
C. Schedule baseline
D. Cost baseline
1. 在控制采购过程,因为各种原因可能更新以下文件,以下哪个文件具有最小被更新的可能性?
A. 质量管理计划
B. 采购管理计划
C. 进度基准
D. 成本基准
2. After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans?
A. RACI chart
B. Control chart
C. Fishbone diagram
D. Probability and impact matrix
2. 在通过头脑风暴得到项目潜在风险之后,建议用什么方法来排列风险的优先级以及制定减轻计划?
A. RACI图
B. 控制图
C. 鱼骨图
D. 概率影响矩阵
3. During the Manage Stakeholder management process, a number of project documents might get updated. Which of the following project documents get updated the most during this process?
A. Stakeholder register
B. Risk register
C. Project reports
D. Project presentations
3. 在管理相关方参与过程,有一些项目文件需要被更新。以下哪一份文件是在该过程被更新的最多的?
A. 相关方登记册
B. 风险登记册
C. 项目报告
D. 项目演示