欢迎大家来到思摩特合肥PMP培训中心,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1.Work Performance Information is not an output of which of the following processes?
A. Validate Scope
B. Manage Communications
C. Monitor Risks
D. Control Scope
1. 工作绩效信息不是以下哪个过程的输出?
A. 确认范围
B. 管理沟通
C. 监督风险
D. 控制范围
2. You are managing a project that requires an environmental permit to do work. The approval is in the final stages when a confidential, reliable report is brought to your notice. The report indicates there is a high risk of an environmental hazard due to the project. Your manager tells you it is better to keep quiet at this stage since losses from terminating the project might be very high. You must:
A. Send an email to your manager documenting the matter and disowning ownership of the project
B. Inform the necessary authorities of the hazard, even if it means cancelling the project
C. Wait for the project to start and see if the information in the report is true
D. Keep quiet about the matter since you will follow your manager’s instructions
2. 你在管理一个需要环境许可才能开展工作的项目。当一份机密的、可靠的报告被提交给你时,审批处于最后阶段。该报告指出,由于该项目存在环境方面高风险。你的经理告诉你,最好在这个阶段保持沉默,因为终止项目的损失可能非常高。你必须:
A. 向你的经理发送一封电子邮件,记录这件事,并否认该项目的所有权
B. 通知必要的有关部门,即使它意味着取消项目
C. 等待项目开始,看看报告中的信息是否正确
D. 对这件事保持沉默,因为你会听从经理的指示
3. Vendor selection, vendor management, and documentation of lessons learned are tasks that fall under this process:
A. Procurement management
B. Deliverable management
C. Conduct Procurements
D. Scope management
3. 供应商选择、供应商管理和经验教训的文档都是在哪个过程中完成的任务:
A. 采购管理
B. 交付管理
C. 实施采购
D. 范围管理