欢迎大家来到思摩特杭州PMP培训中心,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. Projects are often started as a result of an external factor such as market demand for a new product, a new legislative or regulatory mandate, or a change in technology. This results in the creation of ( ) by an entity or organization external to the project.
A. The project charter
B. The WBS
C. The project budget
D. The RACI chart
1. 项目往往是由外部因素启动的,比如市场对新产品的需求、新的法规或监管,或技术的变化。以下哪一个结果是由项目外部的实体或组织创建的?
A. 项目章程
B. WBS
C. 项目预算
D. RACI图
2. Breaking down project activities into smaller components in order to obtain a more accurate cost estimate and then aggregating the estimates of the lower- level components is:
A. Work breakdown structure
B. Analogous estimating
C. Decomposition
D. Bottom-up estimating
2. 将项目活动分解为较小的组件,以获得更准确的成本估算,然后汇总较低级别组件的估算属于:
A. 工作分解结构
B. 类比估算
C. 分解
D. 自下而上估算
3. The Make-or-Buy analysis is a technique used as part of the Plan Procurement Management process. It can determine whether the project team can produce a particular product or service, or if it should be purchased. The analysis to arrive at a decision should include:
A. Indirect costs only
B. Direct as well as Indirect costs
C. Direct costs only
D. Staffing costs only
3. 自制外购分析是计划采购管理过程中使用的一项技术。它可以决定项目团队是否可以生产特定的产品或服务,或者是否应该购买。该分析做出决定时应该包括:
A. 仅间接成本
B. 直接和间接成本
C. 仅直接成本
D. 仅人力成本