欢迎大家来到思摩特长沙PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
01、The agile technique of on-demand scheduling is not suitable when
A. Product deliverables can be incrementally developed.
B. Project requirements can be decomposed into smaller chunks that are relatively similar in size and scope.
C. Project tasks can be bundled by size and scope.
D. The use of a predictive lifecycle is mandated by the customer.
5. 在敏捷项目中,下列哪项按需进度计划是不合适的:
A. 产品可交付物可以增量地开发
B. 项目要求可以分解成较小的部分,大小和范围都比较相似
C. 项目任务可以按大小和范围捆绑
D. 预测生命周期的使用是由客户授权的
02. Which of these is not a component of the scope baseline that is contained in the project management plan?
A. Work Breakdown Structure (WBS)
B. Requirements documentation
C. WBS Dictionary
D. Project Scope Statement
4. 在项目管理计划中,哪项不是范围基准的组成部分?
A. 工作分解结构(WBS)
B. 需求文件
C. WBS字典
D. 项目范围说明书
03. A project’s financial management reserves are determined in which process:
A. Estimate Costs
B. Determine Budget
C. Control Costs
D. Estimate Activity Resources
3. 一个项目的应急储备是在哪个过程确认的:
A. 估算成本
B. 制定预算
C. 控制成本
D. 估算活动资源